How The Space Shuttle Countdown Operates?

Here are some of the key events that take place at each milestone after
the countdown begins.
Note: Event times and lengths are approximate and subject to change.



T-43 hours and counting
The Shuttle Test Director performs the traditional call to stations and the countdown clock is activated.
  • Begin final vehicle and facility close-outs for launch
  • Check out backup flight systems
  • Review flight software stored in mass memory units and display systems
  • Load backup flight system software into the orbiter's general purpose computers
  • Remove middeck and flight deck platforms
  • Activate and test navigational systems
  • Complete preparation to load power reactant storage and distribution system
  • Complete flight deck preliminary inspections
T-27 hours and holding
This is the first built-in hold and typically lasts four hours.
  • Clear launch pad of all non-essential personnel
T-27 hours and counting
  • Begin operations to load cryogenic reactants into the orbiter's fuel cell storage tanks
T-19 hours and holding
This built-in hold typically lasts four hours.
  • Demate the orbiter's midbody umbilical unit
T-19 hours and counting
  • Begin final preparations of the orbiter's three main engines for main propellant tanking and flight
  • Fill launch pad sound suppression system water tank
  • Resume orbiter and ground support equipment close-outs
  • Close out the tail service masts on the mobile launcher platform
T-11 hours and holding
This built-in hold varies in length, but typically lasts 12 to 13 hours.
  • Flight crew equipment late stow
  • Move rotating service structure to "park" position
  • Activate the orbiter's inertial measurement units and communications systems
  • Perform ascent switch list
T-11 hours and counting
  • Activate the orbiter's fuel cells
  • Clear the blast danger area of all nonessential personnel
  • Switch the orbiter's purge air to gaseous nitrogen
T-6 hours and holding
This built-in hold typically lasts two hours.
  • Launch team verifies no violations of launch commit criteria before loading the external tank with propellants
  • Clear pad of all personnel
  • Chill-down of propellant transfer lines
  • Begin loading the external tank with about 500,000 gallons of cryogenic propellants
T-6 hours and counting
  • Finish filling the external tank with its flight load of liquid hydrogen and liquid oxygen propellants
T-3 hours and holding
This built-in hold typically lasts two hours.
  • Perform inertial measurement unit preflight calibration
  • Align Merritt Island Launch Area (MILA) tracking antennas
  • Final Inspection Team proceeds to the launch pad to conduct a detailed analysis of the vehicle as the team walks up and down the entire launch tower
  • Closeout Crew proceeds to the launch pad to configure the crew module for countdown and launch and assist the astronauts with entry into the orbiter
T-3 hours and counting
  • Crew departs for the launch pad and, upon arriving at the pad, begins entry into the orbiter via the White Room
  • Complete close-out preparations in the launch pad's White Room
  • Check cockpit switch configurations
  • Astronauts perform air-to-ground voice checks with Launch Control (Kennedy Space Center) and Mission Control (Johnson Space Center)
  • Close the orbiter's crew hatch and check for leaks
  • Complete White Room close-out
  • Close-out crew retreats to fallback area
T-20 minutes and holding
This built-in hold typically lasts 10 minutes.
  • Shuttle Test Director conducts final launch team briefings
  • Complete inertial measurement unit preflight alignments
T-20 minutes and counting
  • Transition the orbiter's onboard computers to launch configuration
  • Start fuel cell thermal conditioning
  • Close orbiter cabin vent valves
  • Transition backup flight system to launch configuration
T-9 minutes and holding
This is the final built-in hold,
and varies in length depending on the mission.
  • The Launch Director, Mission Management Team
  • Shuttle Test Director poll their teams for a go/no go for launch
T-9 minutes and counting
  • Start automatic ground launch sequencer
  • Retract orbiter access arm (T-7 minutes, 30 seconds)
  • Start auxiliary power units (T-5 minutes, 0 seconds)
  • Arm solid rocket booster range safety safe and arm devices (T-5 minutes, 0 seconds)
  • Start orbiter aerosurface profile test, followed by main engine gimbal profile test (T-3 minutes, 55 seconds)
  • Retract gaseous oxygen vent arm, or "beanie cap"
    (T-2 minutes, 55 seconds)
  • Crew members close and lock their visors
    (T-2 minutes, 0 seconds)
  • Orbiter transfers from ground to internal power
    (T-50 seconds)
  • Ground launch sequencer is go for auto sequence start (T-31 seconds)
  • Activate launch pad sound suppression system
    (T-16 seconds)
  • Activate main engine hydrogen burnoff system
    (T-10 seconds)
  • Main engine start (T-6.6 second
T-0
  • Solid rocket booster ignition and liftoff!


source : http://www.nasa.com

Space Shuttle Endeavour Lifts Off!




Brilliantly lighting up the dark sky, space shuttle Endeavour roared off Launch Pad 39A at 2:28 a.m. EDT Tuesday carrying the STS-123 crew, a module of Japan's Kibo laboratory and a Canadian robotic system to begin the 25th mission to the International Space Station.Brilliantly lighting up the dark sky, space shuttle Endeavour roared off Launch Pad 39A at 2:28 a.m. EDT Tuesday carrying the STS-123 crew, a module of Japan's Kibo laboratory and a Canadian robotic system to begin the 25th mission to the International Space Station.

Source : http://www.nasa.com

STS-123 Ready To Launch


After suiting up, the astronauts made their way out of the crew quarters in the Operations and Checkout Building to the cheers and applause from the crowd of well-wishers as they head for the silver Astrovan that will take them to Launch Pad 39A where Endeavour waits.

Already at the launch pad, members of the Closeout Crew are inside Endeavour as they prepare the crew compartment for the astronauts' arrival. This crew helps the astronauts strap into their seats and prepare for launch.

About the Mission



NASA astronaut Dominic Gorie commands a crew of six, including Pilot Gregory H. Johnson and Mission Specialists Rick Linnehan, Robert L. Behnken, Mike Foreman, Garrett Reisman and Japanese astronaut Takao Doi. Johnson, Behnken and Foreman will be making their first spaceflight.

During the 16-day mission, the crew's two prime objectives are to deliver and attach to the International Space Station the first component of Japan's new laboratory called Kibo, as well as Canada's new robotics system, the Special Purpose Dexterous Manipulator, or Dextre. STS-123 is the 25th shuttle mission to the International Space Station.

Expedition 16 Flight Engineer Leopold Eyharts, who arrived at the station aboard Atlantis in February, will return to Earth with the Endeavour crew as Reisman takes his place on the station.

source : http://www.nasa.com